SITE REPORT NO 3

Dear Blog Viewers,

Another month of construction work sees the structural deck on the hall roof, the start of the flat roof around the hall and the first lift of block and facing brickwork


                                                                                    
Block work for the new plant room is also complete, the timber plant room roof is being built and the mains services ducts are installed in readiness for the October half term Plant Room change over.

Following consultation with the School the internal colour scheme has largely been agreed and the schedules issued for construction.

The Construction works are on programme.

See you next month!