Thursday 10 November 2011

SITE REPORT NO 4

Dear Blog Viewers,

Good progress was maintained on site through October. The brickwork is progressing well; the main hall roof is nearly complete with fascias, soffits and wind catchers still to install. (Wind catchers will provide natural ventilation into the main hall). The new classroom windows are being installed.
                                                             

        


                                                                                        
Over half term, Kier really took advantage of the school without pupils: The windows to the old hall which will become the resource area have been replaced and a new storm drain was installed across the playing field.                                                                            

   

The programme critical work of closing down the old plant room and making the new plant room operational tested everyones nerves to the limit as the utilities were late in installing the meters. However the work was completed late on Sunday 30th October ready for the school to repoen on the 31st.
Well done Kier!