Dear Blog Viewers,
How patiently you have been waiting for my next post and here it is and it will be the last as the extension and refurbishment of Swindon Village Primary School is complete (bar one or two small details!). Kier are finishing off the last touches and the school will open next week free from contractors and all of it open to the pupils.
The final phase was the external works and they do look good. The multi use games area is fenced and lined,
the grassed areas are looking extremely verdant, in fact there has been so much rain that we have been unable to cut it. The fire alarm sprinkler tank is installed and behind a fence!
The refurbishment of areas of the existing school looks good - from the toilets to the resource area...
And of course the new entrance with the welcome sign says it all.
Well done everyone involved - the school, GCC, Kier, the consultants team, but especially the staff and pupils who have had to put up with a lot over the past year. We think it was worth it. We hope you do too.
Swindon Village Primary School
Wednesday, 29 August 2012
Monday, 16 April 2012
SITE REPORT NO 7
Dear Blog Viewers,
Another milestone is nearly upon us, by the end of this week (Friday 19 April) Kier will hand over the rest of the new extension ie the main entrance, admin offices, new hall and kitchen, community entrance, kitchenette and a few other useful spaces.
I haven't managed yet to photograph the 4 new classrooms and break out corridor but I am told they are functioning well and the School are really pleased with them. Here they are from the outside.
and a few more spaces... the food tech room....an accessible wc.....and back to the stunning main entrance.
So good luck finishing off this week, we can't wait to see it complete. Then on with external works... but more of that next month.
Another milestone is nearly upon us, by the end of this week (Friday 19 April) Kier will hand over the rest of the new extension ie the main entrance, admin offices, new hall and kitchen, community entrance, kitchenette and a few other useful spaces.
I haven't managed yet to photograph the 4 new classrooms and break out corridor but I am told they are functioning well and the School are really pleased with them. Here they are from the outside.
I have photographed the phase just about to be handed over so here is a sneak preview.You will have to ignore all the clutter and the busy but cheerful workers.
First of all the main entrance from inside. Then the main hall and the kitchenand a few more spaces... the food tech room....an accessible wc.....and back to the stunning main entrance.
So good luck finishing off this week, we can't wait to see it complete. Then on with external works... but more of that next month.